Project timeline
- Planning phase: Complete by April 2010
- Design phase: May 2010 to October 2011
- Construction phase: June 2012 to December 2015
The project will require several actions by the water district Board to complete the anticipated work. Below is a list of the actions and when these items are estimated to be brought to the Board for approval.
Adopt Planning Study Report and authorize staff to proceed with design: April 2010
Certify Final Environmental Impact Report and Approve Project: December 2011